FI$Cal’s Governing Entities Have Extended the Project Completion Target by Two Years While Struggles with Financial Reporting Persist

Report Number: 2020-039

Figure 1
The Project Office Has Missed Many Target Completion Dates for FI$Cal

A timeline built of overlapping arrows that show the project’s most recent five target completion dates, four of which the project has missed. Starting on the left hand side is the first arrow showing a completion date of July 2016. The second arrow ends at July 2017. The third arrow ends at July 2019 and the fourth arrow ends at June 2020. The project has set all these dates as completion dates and has missed them. The fifth and last arrow ends at June 2022 and that completion date is the current deadline to finish the FI$Cal project.